Downtown Public Rest Room Facility Progresses

The bid opening for the downtown public bathroom was held on April 18th at 11:00 am.  The City received three bids for general construction with the low bidder being A. Chappa Construction LLC in the amount of $162,503.  Haucke Plumbing & Heating has the plumbing contract at a cost of $25,219.  The Common Council awarded the contract at the April 25th meeting.  The bathroom project is scheduled to begin in May 2017 and be completed by early July 2017.  Construction drawings of the bathroom may be found below.  The project is part of the Stayer Park project which also includes a new shelter, playground, and repaving of parking and drive areas.  All work is scheduled to be done in 2017.

Stayer Park Rest Room Construction Drawings